State Privides Update on Carlsbad Brine Well Remediation Project

WE’RE GETTING AN UPDATE ON THE CARLSBAD BRINE WELL REMEDIATION PROJECT. DARRELL MOODY HAS THE DETAILS…

THE STATE IS USING A SAND BACKFILL METHOD TO STABILIZE THE BRINE WELL. PUBLIC INFORMATION OFFICER
SUSAN TORRES WITH THE ENERGY MINERALS AND NATURAL RESOURCES DEPARTMENT SAYS 10 OF THE 16 POSSIBLE GROUTING/SAND INJECTION WELLS HAVE BEEN COMPLETE AND GROUTING IS COMPLETE IN THREE WELLS…
(CUT)
TORRES SAYS NEXT STEPS INCLUDE MORE SAND BACKFILLING AND WELL INSTALLATION…FOLLOWED BY COMPLETE SONAR SURVEYS WITHIN THE VOID LOCATED IN THE NORTHERN PART OF THE SITE.